Iron recovery, dry stack tails approved for Altiplano’s El Penon plant at Farellon - Canadian Mining Journal

2021-12-23 07:43:06 By : Mr. Owen du

Altiplano Metals (TSXV: APN) has received approval from the Chilean mining authority to include an iron separator and a high-efficiency water recovery circuit at its El Penon mineral processing facility to support the Farellon iron oxide copper gold (IOCG) mine near La Serena, Chile.

The dewatering stack will generate a dry tailings product that can be moved and stored in an environmentally efficient manner, replacing a conventional tailings dam system. In addition, the dewatering stack circuit will reduce the overall freshwater consumption needed at the plant by approximately 75%. 

The mill flowsheet includes conventional flotation and a filter press to produce a 26.5% copper concentrate with gold credits. The addition of three magnetic separators and a drum filter will produce a 61% iron concentrate for sale. Together, these processes will reduce the amount of tailings material by 50% compared to similar plants treating ICOG ores. The tails will be thickened, filtered and reduced to 10% to 15% moisture content before stacking. The water recovered will be recycled.

Altiplano says the plant will produce 1,850 tonnes of iron concentrate and 300 tonnes of copper-gold concentrate each month.

The new mill is to be operational in the first quarter of next year. Visit www.APNMetals.com.

Your email address will not be published. Required fields are marked *

Save my name, email, and website in this browser for the next time I comment.

Canadian Mining Journal provides information on new Canadian mining and exploration trends, technologies, mining operations, corporate developments and industry events.